NO "GET Track" if Track / bridge added before H4

xcrossi

New member
Hello:
I can move,change height and delete.
Cannot "GET TRACK" if placed before H4.
I can place the same track/bridge and come back later and GET TRACK (Highlight).
Track /bridges will not highlight if placed before H4.

Nothing is LOCKED
 
There are some splines which give problems when elevated 10 metres, or more, above relative ground level.

They will behave again if the remove gradient button us used to flatten them, or the height is reduced to less than 10m. It's then just a simple matter to deal with them as you want and re-elevate them to the required level when done.

Advance apologies if this doesn't solve the problem because I've no idea what H4 means.:o
 
HOT fix 4
or build BUILD 61388

Well I be! You are correct....:p
The bridges in question were above 10meters:(
My same test bridge was set a 7meters.:eek:

So many quarks (what ever) to remember.:confused:
 
Last edited: